Which record is typically NOT kept at a construction job site?

Study for the South Carolina Business Management and Law Exam with comprehensive question sets, flashcards, and detailed explanations. Prepare effectively and ace your exam!

Job estimates are typically created during the planning and bidding phases of a construction project and are not regularly maintained on-site. They are used to determine the expected costs and resources needed for a project but do not reflect the ongoing activities or progress once the construction commences.

In contrast, daily logs, material orders, and progress reports are crucial documents that the construction team uses throughout the project. Daily logs document the day-to-day activities, worker attendance, and any issues that arise on site. Material orders track the procurement of supplies necessary for the project, and progress reports provide updates on how well the project adheres to its timeline and budget. These records are essential for effective project management and communication among stakeholders during the construction process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy