If a contractor faces liquidated damages of $750 a day for overextending the project by eight days, what is the total amount due considering four days were caused by rain?

Study for the South Carolina Business Management and Law Exam with comprehensive question sets, flashcards, and detailed explanations. Prepare effectively and ace your exam!

To determine the total amount due in liquidated damages, one must first identify how many days the contractor is responsible for the delay, excluding those days that are not attributable to the contractor’s actions. In this scenario, the contractor faces liquidated damages of $750 per day for an eight-day overextension.

Since four of those eight days were caused by rain, which is typically considered a force majeure event and beyond the contractor's control, those days should not count against the contractor. Therefore, the applicable delay days for which the contractor is liable are limited to the remaining four days.

To calculate the total liquidated damages owed, multiply the daily rate of $750 by the four days the contractor is responsible for:

4 days x $750/day = $3,000

However, it seems like this might not align with the expected answer. Clarifying the match:

If one were to consider the entire eight days—without counting rain delays—the total would indeed be calculated as:

8 days x $750/day = $6,000.

Thus, the correct answer accounts for the contractor's liability after deducting the time considered excusable due to weather conditions, leading to the result of $3,000.

It's meaningful to note that liquidated damages

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy